Sample Implementation Schedule
|
Legal
Technology Institute |
Phase 1
| The following is a list of goals and milestones to accomplish during Phase 1 of the Case Management System implementation. | |
| Install case management system software | |
| Integrate with existing computing environment | |
| Customize case management system screens and menus | |
| User training on case management system overview | |
| User training on case management system data input, creating new cases | |
| Administrator training on case management system | |
| Input all new cases | |
| Input all clients, contacts into case management system rolodex | |
| Develop plan for inputing active cases | |
Phase 2
| The following is a list of goals and milestones to accomplish during Phase 2of the Case Management System implementation. | |
| Implement calendaring function | |
| Implement diarying function | |
| Implement reporting function | |
| User training on calendar function | |
| User training on diary function | |
| Administrator training on report writer | |
Phase 3
| The following is a list of goals and milestones to accomplish during Phase 3of the Case Management System implementation. | |
| Implement document generation function of case management system | |
| User training on document generation | |
| User training on coding documents | |
| Administrator training on document generation | |